Skip to content

303-306-9191

CST-Logo-Color-01
  • Services
  • Case Studies
  • Technologies
  • About Us
Free Consultation

Commercial

Commercial Foundation Repair
Concrete Slab Lifting and Leveling
Increased Load Bearing Capacity
Rocking Slab Stabilization & Undersealing
Soil Densification & Recompaction
Trip Hazard Elimination
Void Fill

Industrial

Carbon Fiber Structural Reinforcement
Grout Curtain Cutoff Wall
Industrial Concrete Lifting & Leveling
Industrial Corrugated Metal Pipe Repair
Industrial Foundation Repair
Tank Equipment & Pad Leveling

Residential

Driveway and Sidewalk Lifting & Leveling
Expansive Clay Soil Treatment
Floor Slab Leveling
Residential Foundation Repair
Swimming Pool and Deck Lifting
Soil Compaction & Void Fill

Transportation

Airport and Taxiway Pavement Lifting & Leveling
Bridge Approach Lifting
Concrete & Asphalt Pavement Lifting
Corrugated Metal Pipe Repair for Transportation Projects
Frost Heave Mitigation
Infiltration Mitigation
Infrastructure and Joint Sealing
Railroad Crossing Void Lift & Slab Fill
Subgrade Soil Stabilization and Densification
Our Engineering Partners
Blog & News
Meet Our Team
Free Consultation
Search
Close this search box.

Case Study

LDS Meeting House

Foundation settlement in a meeting house was causing ongoing damage to the structure. Our repair methods stopped further damage in its tracks.

Project Summary

CST lifted and stabilized the foundation of a Church of Jesus Christ of Latter Day Saints building in Malta, Idaho, with its deep injection method. Soil analysis enabled an engineered plan to address weaker soil zones, and work was completed in three shifts with no excavation and repairs made in days.

The Church of Jesus Christ of Latter Day Saints Second Ward Meeting House, located in Malta Idaho, had been foundation settlement and movement in portions of the building, resulting in ongoing damage to the structure.

In the spring of 2014, LDS structural engineer, Chris Barker contacted CST’s Utah Field Consultant, Jonathan George, concerning a repair plan for the structure.

Malta Idaho is a small community located in south central Idaho. Agriculture is one of the main industries in this area. Water being pulled from aquifers for irrigation throughout the area has lowered the water table. With change to the ground water and water table below the surface, pressure areas change and shifting of soil and rock below the surface take place. Sometimes, this occurs at depths very far below the surface.

Engineering reports indicated that settlement and shifting of the soils at a considerable depth, as suspected, were likely the cause of the extensive foundation settlement and sideways movement occurring at the LDS building.

A measuring device which had been installed on the building in early spring of 2014 showed movement of 3 millimeters over a period of 4-5 months.

CST met with the LDS maintenance personnel on site and performed investigative Dynamic Cone Penetrometer tests.

Test results determined that most of the settlement was not related to the upper 15 feet of soils, lending support to the conclusion that movement was coming from considerable depth.

After a thorough site investigation and analysis of soil tests, CST proposed to employ the CST deep injection method in order to lift and stabilize the building’s foundation both around the perimeter of the building and the load bearing footers and walls on the interior. DCP tests verified soil conditions in order to create an engineered plan to address the weaker zone of soils.

Soils directly below the foundation were dry and ideal for effectively lifting and stabilizing the structure to mitigate future movement and damage.

On May 5, 2015 CST crews arrived on site. A walkthrough was made to identify all crack openings and other damage that had been caused by the settlement and sideways movement of the building. CST’s crew members began drilling injection holes on the exterior of the building near the foundation to identify the spread footer. Probes were then placed on 4 foot centers approximately 3’ to 4’ below the spread footer. Other members of the crew began drilling and preparing interior injection holes and probes and drafting the exterior survey.

On day two, crews prepared equipment to begin injections and starting on the west exterior corner, technicians began injecting structural polymer at set locations. The foundation responded and began moving quickly. Some of the exist-ing cracks began to close at this point. Crews moved back and forth in the west corner section until a total lift of 3 ½ inches was accomplished on the exterior portion of the foundation.

On the final day, crews moved to the interior of the building and complete injections to lift the slab to target elevation.

Result: The load bearing wall was lifted, stabilized and void fill completed in the treated areas. As a result, existing cracks were closed in damaged areas. Movement of the building was greatly arrested and mitigated against further structural damage. All work was completed in three shifts.

Benefit: The CST technologies require no excavation and are performed with very little disturbance or mess. Repairs are made in days, not weeks or months. No need to vacate buildings and treated areas may be used immediately following repairs.

About the Project

Location

Malta, Idaho

Project Date

May 2015

How We Helped

Contracting Investor

Church of Jesus Christ of Latter Day Saints

Project Highlights

Related Services

Airport and Taxiway Pavement Lifting and Leveling

Bridge Approach Lifting

Carbon Fiber Structural Reinforcement

Commercial Foundation Repair

Concrete and Asphalt Pavement Lifting

Concrete Slab Lifting & Leveling

Corrugated Metal Pipe Repair for Transportation Projects

Driveway and Sidewalk Lifting and Leveling

Expansive Clay Soil Treatment

Floor Slab Leveling

Frost Heave Mitigation

Grout Curtain Cutoff Wall

Increased Load Bearing Capacity

Industrial Concrete Lifting & Leveling

Industrial Corrugated Metal Pipe Repair

Industrial Foundation Repair

Infiltration Mitigation

Infrastructure and Joint Sealing

Railroad Crossing Slab Lift and Void Fill

Residential Foundation Repair

Rocking Slab Stabilization and Undersealing

Soil Compaction and Void Fill

Soil Densification & Recompaction

Subgrade Soil Stabilization and Densification

Swimming Pool and Deck Lifting

Tank Equipment & Pad Leveling

Trip Hazard Elimination

Void Fill

Project Gallery

Wall Cracks; Foundation Lift
Recommended Case Studies
Buffalo Pool Void Fill[1]
City Swimming Pool Void Fill Soil Stabilization
Read More
Void Fill Soil Stabilization
Irrigation Head Gate Void Fill Erosion Control Soil Stabilization
Read More
CMU Carbon Fiber Repair
Carbon Fiber Structural Repair Exterior Block Wall
Read More
CST Foundation Lift 2017
Foundation Stabilization and Lift
Read More

Concrete Stabilization Technologies, inc.

  • info@cststabilization.com
  • Open Weekdays 9am - 5pm MST
  • 303-306-9191
Get In Touch

INdustries We Serve

  • Commercial
  • Industrial
  • Residential
  • Transportation
  • Commercial
  • Industrial
  • Residential
  • Transportation

How We Help

  • Read Our Case Studies
  • Technologies We Use
  • Read Our Case Studies
  • Technologies We Use

our company

  • Our Team
  • Our Engineering Partners
  • News
  • Careers
  • Our Team
  • Our Engineering Partners
  • News
  • Careers

Areas We Serve

  • Colorado
  • Colorado Springs
  • Denver
  • Utah
  • Salt Lake City
  • Wyoming
  • Montana
  • Colorado
  • Colorado Springs
  • Denver
  • Utah
  • Salt Lake City
  • Wyoming
  • Montana

Concrete Stabilization Technologies, Inc. Ⓒ 2023 | All Rights Are Reserved

Designed and Developed by GEOCMO